how many days we should curing for
plastering,brickwork,concrete?

Answer Posted / ram mohan rai

Curring should start as soon as concrete start hardening
till at least 7 days depend upon weather condition.

Is This Answer Correct ?    12 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1

1587


WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?

1856


At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.

1688


psc girder detail

2716


what do you understand by M25 concrete

1930






How many pyramid in egypt?

639


how we can find sieve #4 is 4.75mm?

1877


How much for the BRC lapping in full yield and half yield < and which table to get it ?

2030


for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete

1481


What is the difference between Grade I, II and III of GSB?

1903


how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation

1219


writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order

1490


What black man invented the clothes dryer?

687


column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial

3492


sir, whitch is the best book (writer name) for prepration of gate....

1212