Answer Posted / guppi chandra sekhar
Calculation of materials for 1cum of 1:6 Cement Mortar by
Volumetric method:
Specific Gravity of Cement = 3.15 ; Density of Cement =
1440kg/cum
Specific Gravity of Sand = 2.6 ; Density of Cement =
1550kg/cum @ 5% moisture
First of all we have to calculate yield of 1 cement bag
(50kg) mixed in 1:6
Volume of Cement = (50/1440) = 0.03472cum
Volume of Sand mixed = 6 X 0.03472 = 0.208cum (contains 5%
moisture)
Volume of only sand = 95% of 0.208 = 0.198 cum
Absolute volume of Cement = 50kg / (3.15X1000) = 0.016 cum
Absolute volume of sand = Weight of sand / (2.6 X 1000) =
(0.198 X 1550) / (2.6 X 1000) = 0.118 cum
Let volume of water added = 30litres = 0.03 cum
Moisture present in the sand = (0.208 - 0.198) = 0.01 cum
Total volume of water = 0.03 + 0.01 = 0.04 cum
Let, Moisture content in the mortar = 2% of yield
Let, yield = Y
(1-2%)Y = Absolute volumes of (Cement + Sand + Water) =
0.016 + 0.118 + 0.04 = 0.174 cum
Total Yield Y = 0.174 / 0.98 = 0.178 cum
1bag of 50kg Cement produces = 0.178 cum of 1:6 Cement
Mortar with 0.208cum of Sand @ 5% Moisture and 30 litres of
water.
Therefore, 1 cum of 1:6 Cement Mortar requires :
Cement = 1bag X 1/ 0.178 = 5.62 bags
Sand = 0.208 X 1 / 0.178 = 1.17 cum
Water = 30 X 1 / 0.178 = 168 .5 litres
| Is This Answer Correct ? | 55 Yes | 21 No |
Post New Answer View All Answers
Detection of a beam & a girder areββββ
How to calculate paint drums per meter square
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
What are the different types of civil engineering?
For Granite Flooring,For Cement Slurry purpose which one is effective of cost control whether OPC or PPC or White cement?
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
1m square 20mm plastering how much of water need curing work
What is the origin of name railway sleepers?
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
pls mail some more tecnical qustions at msaranya2610@gmail.com
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
What are the applications of cad?
Formula for calculating the volume of bulb in underreamed pile
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
Define absolute co-ordinates?