how many bags of cement required in neat cement finish per
square metre

Answer Posted / kumar

above answer is wrong. simply

for one Sqm of neat Cement Finish With 15 mm thick plaster -
0.145 Bags of Cement Required For Sqm.

Calculation = 0.145 * 290=42.05
Sand = 0.015*1260 = 18.9
total Material Cost = 60.95
Labour Cost is = 90 / SQm
So all together = 150.95 Say 150.

from ur calculation

for one Sqm = 32.5 kg of cement
that means = 32.5 X (290/50)= 188.5 / Sqm
is it Any boq Neat Finish gave above 300/

Is This Answer Correct ?    4 Yes 19 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is castigliano theaorem

1833


please briefly explain calculating or estimating steel quantity for a RCC column?

1439


Would you cause a 55-gallon drum of water to weigh more by climbing in?

674


how much is the maximum compressive strength of soil cement and soil-cement-microsilica .

1821


What is passive earth pressure ?

717






if the nitrates more than 45mg/l in water lead to disease then what is it called

2340


What are your future hopes for this job?

1833


What is critical path method (c.p.m)?

697


What are the responsibilities of a site manager?

621


Mention what are the composition of a landfill?

724


what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.

1739


Wat is meant by Aecron brick?

1649


Define Workability ?

787


What is the procedure of concealed plumbing in toilets?

1889


How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?

5814