How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?
Answer Posted / arjun
1:4 (or) 1:6
| Is This Answer Correct ? | 30 Yes | 17 No |
Post New Answer View All Answers
What are new methods /technologies of pothole patching?
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
What is construction mitigation management?
What is the veriplus for ellips card length formula (major axis 3.4m,minar axis 2.6m spacing 0.2m
how to tie 10 legged stirrups
Why the finite element method is lower bound solution?
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
what would be the design load of R.C.C Cooling tower per cell.?
What things you need to take care of before building a kitchen island?
What are the RISKS during the project construction?
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
How to calculate laplength for 3 floors