Question what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?
 Question Asked In Companies :: ABB, L&T, Saudi Oger, Construction, l, Isher, Spectra, Strati,     < I also faced this Question! >
 Question Submitted By :: shaunpaulstar
  Answer Posted By  
 
Answer
Generally its easy to find it.

Find Total Parts = (1+2+4)=7 Parts.

For 1 cu.m of concrete the total parts = 1.57

Unit weight of cement = 1440 kgs

Cement = (1440/7)*1.57 = 322.97/50kgs = 6.46bags.

1 bag cement= 1.25cft

Sand = 6.46*1.25 = 8.075 cft*2 =16.15 cft

Aggregate = 8.075 cft*4 =32.3 cft.

Thats all...

Result:
Cement = 6.46 bags
Sand = 16.15 cft
Aggregate = 32.3 cft.


Regards,

Er.Vigneshwaran S

Is This Answer Correct ?    4 Yes 9 No


 
  vigneshwaran s
 
View All Answers
 
 
Please Help Members By Posting Answers For Below Questions
 
 Question Views   Select
 
What is construction mitigation management? 512
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work. 336
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building 1096
what is the 0 value in quantity surveying 619
satart to end steps by step process of building construction...? i want to planning theme accuretly 62
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate. 192
for pretensioning which will yield first and same for post tensioning? 421
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer 1237
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab 615
Why the finite element method is lower bound solution? 467
how much one carpenter can doing shuttering of slab in one day 1540
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building? 1709
what is mean by reestimation? 146
pls give me ans to ACT formula cube testing porpuse 1185
can we compare the combined core of DBM and BC density with average density of Lab DBM and Lab BC density 156