how much cement consumption in 1 sqmt of wall cleading work
(dedo)?
Answer Posted / sanchit guleria
thickness of neat cement layer is 1.5mm.
so cement required for 1sq.m= 1*0.0015=.0015cu.m
dry vol. of cement increased by 25% so (.0015+.0015/4)=.001875cum=.054 bag=2.67kg of cement
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
How to make tiles floor step by step procedure?
how to calculate steel for slab or footings?
How does a traffic light signal work ?
How do you calculate reinforcement weight of steel?
The concrete slump recommended for beams and slabs; is?
what is pqc
which has high compressive strength between hollow block and brick masonry?
Coverage of 25mm.thick ratio of 1:4 cement mortar?
what is meant by csr in foundation? what is sbc?what is meant by contour line?
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
i want texture painting pwd data
how much is the maximum compressive strength of soil cement and soil-cement-microsilica .
Explain major difference between auto level and dumpy level?
I'm preparing to to build a simple house, but i don't know how to calculate how much cement, gravel and sand and hollow blocks i need to prepare. How many pcs of 4" or 6" hollow blocks I need for my planned 3mx6m house? thanks.
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.