how to calculate rate analysis of M25 grade concrete
Answer Posted / amit dutta
m 25= 1:1:2.
there ore ratio is 1+1+2=4
we know one cub dry volume is 1.54.
there fore cement require,
1.54*1/4=0.385=11 bags cement for 1 cub m.
sand =0.3858*32.28cft = 12.45 for one cub m.
stone chip 0.77*32.28cft = 24.85 for 1 cub m.
Is This Answer Correct ? | 58 Yes | 40 No |
Post New Answer View All Answers
Explain different types of rcc pipes.
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
For a washout valve why are two gate valves required in normal practice?
What is aggregate?
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
In case if concrete box girder bridges how is the number of cells determined?
What are the skills required to become an architect?
3. What are the disadvantages of your present job, things you do not like about it?
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
What is difference between engineering stress and true stress?
Can inverted beams used in pipes during construction?
Formula of area of crane hook
what is the difference between natural draught cooling tower and induced draught cooling tower
crank types
What is construction mitigation management?