m 25= 1:1:2.
there ore ratio is 1+1+2=4
we know one cub dry volume is 1.54.
there fore cement require,
1.54*1/4=0.385=11 bags cement for 1 cub m.
sand =0.3858*32.28cft = 12.45 for one cub m.
stone chip 0.77*32.28cft = 24.85 for 1 cub m.

Is This Answer Correct ?    58 Yes 40 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain different types of rcc pipes.

711


We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?

1605


For a washout valve why are two gate valves required in normal practice?

675


What is aggregate?

737


If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.

1553






In case if concrete box girder bridges how is the number of cells determined?

713


What are the skills required to become an architect?

651


3. What are the disadvantages of your present job, things you do not like about it?

2291


TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING

2105


What is difference between engineering stress and true stress?

672


Can inverted beams used in pipes during construction?

874


Formula of area of crane hook

1527


what is the difference between natural draught cooling tower and induced draught cooling tower

1831


crank types

1888


What is construction mitigation management?

1843