i need the how much materials are needed for cubic feet of
concrete?
Answer Posted / guest
FOR PROPORTION 1:2:4 FOR 1CU-MT WORK OF CONCRETE CEMENT REQUIRED AS FOLLOWS
CEMENT ---6.5 BAGS
SAND ----0.434 CU-MT
KANKAR --0868 CU-MT
Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
400 ku d/c clearess ketan hota hai?
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
What is the Unit weight of coarse sand (F.M- 2.20) ?????
What are the applications of the modulus of elasticity?
What is the diff between cad & cadd?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
why we use 19x9x9and 20x10x10 but not other
An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.
Define What are the uses of Groynes?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
Prepare a Schedule for a Highrised building from starting stage to Handover?
How to do base isolation using ETABS software?
is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.
115mm thickness brick work how to required mortar