9*9 1:4:8 ratio using how to calculate the material for
40mm aggregate ,cement &sand please tell me answer
Answer Posted / ronak shah
first of all i m not understand 9*9.
so i consider 1m3
52% more shrinkage and wastage.
1.52m3
cement= 1.52/(1+4+8)=0.1169/(cement bag volume in m3)=
0.1169/0.0348= 3.35 bags so 168 kg/m3.
sand=1.52/(1+4+8)=0.1169*4=0.47m3
aggregate=1.52/(1+4+8)=0.1169*8=0.94m3
Is This Answer Correct ? | 47 Yes | 5 No |
Post New Answer View All Answers
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
What is the quantity of cement in mix m20 concrete?
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
I what know about life time of frp tank plz explain about it specifications & other details
how to caliculate required amount of cement and sand required for 1cu.m.
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
How can I make justification between using concrete grade c35 compare c37?
Which Types Of Bricks ?
how to stop beam concrete between column
What do you mean by honeycomb in concrete?
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
What is the density of Fiber reinforced concrete and give me the which fibers we can use in Concrete?