Answer Posted / jigar soni
AS PER I.S CODE MAXIMUM SILT CONTENT SHOULD NOT BE MORE THAN 8%.
BUT AS PER THE SITE CONDITION WE CAN ALLOW SILT CONTENT UP
TO 12-14%.
CEMENT CONSUMPTION WILL INCREASE BY THAT MUCH %.
Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
How to calculate laplength for 3 floors
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever
How to calculate sand , cement quantity for 23mm thk brick work(10x10)
Define What materials were used to build the Golden Gate Bridge?
IN Compression testing machine 1division =10KN ,then what is compressive strength of 100*100 mm cubes at a load of 320 KN
how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?
How much quantity of cement,sand,stone used to build 1 cum of cc road??
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
what is Brest Wall?
How do you calculate load bearing capacity of a waffle slab?
What is the strongest bridge for a school contest?
What are the strongest shapes in building?
what is the theoritical percentage of concrete cubes testing per day?
what are the duties of Site Engineer in work site?