in a transmission line if the load is suddenly increased in
the receiving end of the system the phase shift will ?
Answer Posted / vijay balu raskar
As power flows along a transmission line, there is an electrical phase shift, which increases with distance and with power flow. As this phase shift increases, the system in
which the line is embedded can become increasingly unstable during electrical disturbances.
Simply, load suddenly increases phase shift will increases.
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
HOW TO CALCULATE HV CABLE SIZING?
we use 400/5A ct and 35/roor3KV,/0.1/root3KV,0.1/root3KV pt ratio. What is the multiple factor of this meter.
Why field rheostat is kept in minimum position while armature rheostat at maximum position?
What is George phenomena to start the synchronus machine?
how we do Vector group ,magnetic balance and tap changer test in Transformer?
In our factory so many iron pillors are exists for supporting the shed/Hangar. If do more no of earthings at one piller instead of doing more earth pits in many locations and running earth strip around the hanger, I can save the money. Please suggest this method is acceptable as per Is specifications though the Earth resitance of the farthest piller is with in the limits as per IS specifications.
how braking & making capacity of circuit breaker are calculated?
Is the theorem applicable to ac sources?
why does the magnetic balance tests at transformer?
Is it possible to implement Restricted Earth Fault protection for a transformer without neutral CT?
in control panel, how can i measuring the distance between one bus bar to another bus bar. then now only for bus bar. in mpcb and contactor also. that means one mpcb to another mpcb how much distance? how can i calculate that.
how you taken aotitude test
iam preparing for rrb section engineer post in electrical branch.suggest the right textbook for my reference.fromwhere i will get the previous q.papers?
What is polar plot?
why it is not advisable to run low rating (19KVA) DG sets in parallel for long durations even though they are provided with droop ckts (QDC)