how to calculate quantity of cement and sand for plastering works in CM 1:6 proportion.....plz answer anyone.....and write the formula...

Answer Posted / rambabu penkey

1;6 PER CU M=1.3 CU M SAND=1.3/6*5=1.08 CUM
1.3/6*1=.216CUM
.216*1440=311.04KGS

Is This Answer Correct ?    3 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.

1489


1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.

2238


How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight

1432


how many time use of plywood shuttering and IS code

2684


GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?

6830






What are your future hopes for this job?

1829


What Reinforcements Are Used In The Process Of Prestressing?

832


please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)

1342


what is smart building materials?

1582


WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)

3251


How to calculate brick work quantity?? Block work quantity??

2107


how to caluclate sienerge qty in construction in ap

1896


is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.

1573


how to prepare site mix design

1547


How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57

1497