A bill was raised by contractor which read as follows
1.) Excavation in normal soil upto 1.5m - 250 cum
2.) Excavation in normal soil 1.5m to 3m - 240 cum
3.) Excavation in soft rock - 350 cum
4.) Excavation in hard rock - 250 cum
5.) Filling with available soil - 825 cum
6.) Filling with bought out soil - 1100 cum
How can I verify the above quantities, especially for item
no. 5 & 6?
What checks are necessary before releasing the bill ?
Answer Posted / gkreddy
contractor should be ansure there must
and should maitain JMR( Joint
Measurement Record) for produce the bill
otherwise bill should be rejected.claint
also insist the contractor to maitain JMR.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
what is the use of water bar in water tank and is this an extra item in estimate?
What is unit weight of roadway layer.. 1.bitumen 2.sand 3.soil 4.concrete 5. aggregate give me some reference for this answers
What is the compressive strength of fly ash bricks?
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
What is a hatch patterns?
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
In cement concrete how to check a quality of material also proportion of material at site ?
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
What is a tensile strength? What is the tensile strength of wood?
how to calculate MR 9(derivation)
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
what is pouring and explain
Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.
give me the mix proportion for design mix concrete M 7.5 grade 1:4:8