who's take first position in process in the timing of new
installation flow transmitter and control vavle. give the
answer with logical trick.
Answer Posted / rahul nayak
obviously the control valve should be installed first.
because we must restrict the flow first by placing valve in
line. then only we should think about to control the flow by
flow transmitter.
Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
what is RTV function in in process control?
please send me some question papers of HPCL aptitude test ?? please send it to bipinb.28@gmail.com ...
What types of Instrumentation Related Questions can an Interviewer ask in a Telephonic Interview ?
Calibration of controller (pneumatic)
What is instrumentation instrumentation engineering?
why we take %i0.0 as input for twido plc
Meaning of the following a. IOP- Manimum; b. IOP- Maximu,;
if my flow is 20000 m3/h than which range of DPT i have to use????
What is Droop? What is Step/Gradient Limiter in Turbine Governor control?
hi sir yhis is zahid ali i am preparing for the jspl at oct.4.please send me the recently updated sample paper.
line up procedure for dp type flow transmitter?
Can any body help to get Rsemulator 5000 free from internet if possible then give me any link or any help .
Why 4-20 amps is being used in instruments? Why cant we use any other range instead of 4-20 amps? Why only 4 amps is taken as lower limit and why 20 amps is taken as the higher limit?
why fuse block is not used for AI signal?
what is different between 2,3&4 wire rtd and how much maximum distance using plc to field.