Answer Posted / mohammad
Earthing Switch is necessary to earth the conducting parts
before maintenance and also to provide deliberate
short-current while testing.This enables various tests to be
performed on the Switchgear or item of equipment, such as
testing the current Transformer of measuring the operating
time of breakers, without having to open the enclosure.
During normal operation the insulation is bypassed by a
short-circuit-proof link.
Is This Answer Correct ? | 28 Yes | 7 No |
Post New Answer View All Answers
how freewheeling diode improves the powerfactor
Why let through energy not considered for ACB breaker while cable sizing?
What is highest size of HT motor like 11 kv or 33 kv,and how to make it 750 rpm.i think the size will be very big.any idea ? pl. reply..
does any one know where we can purchase insulation oil for high voltage oil filled cables
What is Anemometer used to measure?
what is mathed of check the D.C MOTOR 181 KW (ARMATURE AND FIELD) WHAT IS THE MATHED OF CHECK THE THYRISTOR MODULE (HIGH CURRENT)
What is difference between unity power factor wattmeter and upper power factor wattmeter? In short circuit test of transformer the wattmeter used is unity power factor type or upper power factor type wattmeter?
what is subtransient , transient and steady stateac components
How to determine alternating current frequency?
As we know diode work on both negative and positive but converting ac into DC we have to given a/c from negative of diode or positive side.please give me answer.
PLEASE ANYBODY HAVE ELECTRICAL CIRCUIT DIAGRAM FOR CHMER PULSE CD 60M SPARKING MACHINE.PLEASE MAIL ME SUPRIYAAYYAPPAN@YAHOO.CO.IN.
What is genrally the % Impedance of a Dg set? How can we calculate Earthing conductor size for a DG set?
how much UPS neutral erath leakage current.
In Electrical 'Single Line Diagram' cable nomenclature shows "2 X 1C X 630sq.mm to be provided for one incomer. The question is how many cable to be proved for one Incomer.
Dear all: Recently we got a question about Interface between PMS and SAP-PM.once we got a update message from PMS.we should set the deletional flag for functional location in SAP system.Is there any FM or BAPI to use?There are only functional location create and change provided by SAP. Best regards!