how many no of solid blocks and bricks required for construction of wall for 100 sqft?

Answer Posted / saravana prasad chandrababu

Indian Brick Standard Size 9inches*4.25inches*2.75inches
Therefore depends on lenght and breadth it varies,for
instance if it is (L*B)9 inches *4.25 inches wall then for
1 sq.ft it requires 3.76 bricks [MAXIMUM], excluding of
mortar,if it is (L*B)9inches *2.75 inches wall then for 1
sq.ft it requires 5.81 bricks[MAXIMUM} ,excluding
mortar.When mortar is added based on thickness of mortar
the following bricks will be reduced accordingly.

Is This Answer Correct ?    54 Yes 16 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.

2150


What is the procedure of concealed plumbing in toilets?

1883


Which are the top apps for you civil engineer?

717


Cement consumption of one cubic meter of aerocon blocks masonry?

3661


What are the advantages and disadvantages of using plastic and timber fenders?

670






how much one carpenter can doing shuttering of slab in one day

2874


Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?

1392


How do we determine the specific gravity of a cement?

649


What should be the standard roof height like to be?

660


How to do rate analysis for concrete work including shuttering work?

1546


any book or article on pumped concrete.

1722


As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.

1423


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

1669


Explain what are the phases inspections are done by local authority while construction?

737


Difference between pre-tensioning and post-tensioning.

678