Answer Posted / anup sharma
Old roof nd new roof are joined using hilty.
Hilty is the process in which a hole is made in the older
roof by drilling and hilty chemical is inserted inside the
holes and finally new reinforcement is inserted inside these
holes such that the older and the newer reinforcement stay
connected. after that form work is done and the new roof is
casted.
Is This Answer Correct ? | 10 Yes | 2 No |
Post New Answer View All Answers
why is the column design?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
How much for the BRC lapping in full yield and half yield < and which table to get it ?
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
how can we calculate steel value, depending on load
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
what are the types of dimensioning?
which steel is better for residential building tmt steel or hysd steel
For fine aggregate which is most suitable River sand or crusher sand & why ?
What is the average density of soil?
How is make concrete cube?
How to check slab shuttering level.? Or check list for slab ?
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.