concrete strength process timing is 1 year
after 28 days concrete gets 90% strength
then
for - M15=1:2:4=15+1.5=16.5 n/mm^2
for - M20=1:1.5:3=20+2=22 n/mm^2
for - M25=1:1:2=25+2.5=27.5 n/mm^2
& above the m25 grade,that is Based on design mix per IS.
for find strength of above m25 grade strength=concrete strength after 28 days+10%strength of concrete getting strength after 28 days
getting m45 grade strength laboratry test used
ther generally cement ratio increased & test & test till geting m45 strength
Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
how to calculate spacing rod in column
3. What are the disadvantages of your present job, things you do not like about it?
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
Minimum and maximum size of the building components
What Are The Different Type Of Slump Test Indications?
what is the productivity in aluminium shuttering per day
Forces in a Shear Wall are in plane or out of plane ?
if the nitrates more than 45mg/l in water lead to disease then what is it called
How to calculate brick work quantity?? Block work quantity??
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?
within an emergency scenario what are the safe systems of work a coss can setup as part of is duties
Explain what is alternate bid?
How to calculate Volume of Wet cement concrete for a specific grade?
on what basis the partial factor of safety are decided? form the load combinations