How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / abid nawaz
10' x 10' x 0.0333'
3.33 cft
Dry metarial in one cft = 1.27 cft
3.33 x 1.27
4.229 cft
sum of ratio = 1+5 = 6
quantity of cement = 1*4.229/6
= 0.7048 cft
volume of one bag = 1.25 cft
=0.7048/1.25
=0.56 cement bag
quantity of sand = 5*4.229/6
= 3.524 cft
Is This Answer Correct ? | 76 Yes | 18 No |
Post New Answer View All Answers
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
How long does it take concrete to harden?
Where can I get a Text Book on Design of Blast Resistant Buildings in PDF form.
is basic cost of the material includes tax?
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
What is the use of extruded feature in solidsworks?
During reclamation how can the occurrence of mud waves can be rectified?
Define the various stages of the project planning process in construction.
Define aligned dimension?
HOW MANY BAGS OF CEMEMT USED IN PER M2 OF PARTITION WALL
please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering
Why does the pressure increase under soil?
strength vs shape factor
What is construction mitigation management?
how much quantity of cement,sand and water required for 1 sq feet flooring work .