Answer Posted / yisahak
Generally form-work shall be stripped off after the concrete has attained 50% of the 28 day cubic strength, or when it attain twice the stress it will then be subjected after the removal of the form-work, which ever is greater.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
what is tension & compression of steel bending.
What quantity of 1.0 m3 bricks required?
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
What are some facts about concrete?
What is the substitute of Mastic Asphalt?
How can we demolish concrete beams?
How to calculate quantity of cement , sand and granite from concrete mix ratio and volume of work
How will be cutting in timber plate size 600*400 column size
What is the difference between built area and super built up area?
How do you change a dimension value in solidsworks?
any book or article on pumped concrete.
How much quantity of cement,sand,stone used to build 1 cum of cc road??
we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?