Answer Posted / yisahak
Generally form-work shall be stripped off after the concrete has attained 50% of the 28 day cubic strength, or when it attain twice the stress it will then be subjected after the removal of the form-work, which ever is greater.
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What are the disadvantages while using stone dust as filler in pavements?
What are the responsibilities of a construction manager?
20 mpa what is the quantity of cement sand and aggregate in one cubic meter of pcc non rainforcement concreate kindly answer including formaula thanks
How many feet are in 4 square yards?
1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.
What you understand by building codes?
What are the composition of a landfill?
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
I have an span length 16 ft c/c
How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
How you can use different dimension tools in cad? What are the different dimensions available?
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)
How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?