How to calculate compressive strength of concrete?
Answer Posted / r.kumaresan
as per IS 456 3 cubes are mini req for testing the cubes.
prepare the std size 150x150x150 and mix ratio like
1:1:2.make 3 cubes in same ratio and leave 1 day for setting
after 1 day put on curing.if you need 7 days strength after
7 days test the specimen by using comp machine.in 7 days
specimen attain 65% of the target mean strength.in 28 days
specimen attain 90% of the target mean strength.the unit is
commonly used N/mm^2
1N = 1000 kN
Compressive strength =load in newton/Area of cube in mm2
As per thumb rule , at the time of weighing the cubes the
minimum weight of cubes are 8.1 kg
Is This Answer Correct ? | 78 Yes | 34 No |
Post New Answer View All Answers
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
What are the joints wants to made in masonry where door opening, arches like etc..
what is raft foundation
calculate the quantity of water for 1:6 cement mortar
What applicable rate of wct in bihar
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
residential buildings,mixing of concrete,structural,construction material,site handling.
What is made from large rocks, which protects the base of cliffs?
mix design procedure for 1:6 cement mortar
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
What is gravity flow?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
how to design and calculate materail quantity for concrete speedbreaker ?