WHEN BRICK SIZE IS 3X5X9" , WHAT WOULD BE THE NUMBER OF
BRICK REQUIREMENT FOR 100 SQFT AREA OF 5" width?
Answer Posted / srinivas
533
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
Explain what is Critical Path Method (C.P.M)?
What are the strongest shapes in building?
sir, whitch is the best book (writer name) for prepration of gate....
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
How to hide dimensions in autocad?
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
What is the Maximum %age of Steel in columns and beams ?
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
What Are The Steps Involved In The Concreting Process, Explain?
Doul Bar reinforcement and details of drawing.
psc girder detail
can we compare the combined core of DBM and BC density with average density of Lab DBM and Lab BC density