Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.

Answer Posted / dharmesh patel

we can only calculate the quantity in m3 only after that we
can converet in c.ft.
1/4 x 1.54 x 28.8= 11.08 bags cement for 1 m3 for the ratio
of 1:1:2
s0 731 cft = 20.719 m3 * 11.08 = 229.570 bags cement used
1/4 x 1.54 = .385 m3 sand for 1 m3
so 20.719 m3 x .385 = 7.976 m3 sand required in 731 sq .ft
2/4 x 1.54 = 0.77 m3 chips ( aggregate ) for 1 m3
so 20.719 m3 x 0.77 = 15.953 m3 chips required in 731 sq .ft

Is This Answer Correct ?    41 Yes 18 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What quantity of 1.0 m3 bricks required?

1148


is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.

1960


What are the problems one might face while having a Cantilever balcony?

1556


Which are the top apps for you civil engineering?

1163


use ofr concrete as per grade ?

2098


RR masonry rate analysis

3370


i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like

2003


02. a. The diagonal of a 9 cube…………… 1 b. Surface area of 9 cube…………… 1 c. Volume of 1-3 cube …………… 1 d. Compressive area of 6 cube …………… 1 e. Top & Bottom face of a Cylinder/Cube is to be proper leveled to deliver the…………………………..…… properly.

2188


how to find hardness of water?why it should be determined?

2117


What is GSB gradation

2506


what is project?

2387


the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum

2039


How to compute minimum number of columns required for a site from area of site?

2089


hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com

2288


What does civil engineering mean?

1108