how much cement is required for 100 sft plastering of ratio
1:4

Answer Posted / karthikeyan.n

1 sq.m = 10.76 sq.ft.
100 sq.ft = 9.29 sq.m

cement required for 10 sq.m = 3/(1+4)=.6*1440/50 = 17.28bag,

100sq.ft cement required = 1.728*9.29 = 16.05 bags

Is This Answer Correct ?    34 Yes 93 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is made from large rocks, which protects the base of cliffs?

741


How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated

1694


what is Bearing Capacity,How to determine it?

804


How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?

1803


How many types bend used in civil reinforcing

2777






How to calculate density of 40 mm coarse aggregate, in mixing ration 1:1.5:3? Please explain calculation for density

1546


What is the Maximum %age of Steel in columns and beams ?

718


How do you calculate the power of centrifugal pump?

647


does a b.tech civil engineer fresher supposed to know how to design rcc structure?

3009


Explain the advantages and disadvantages of using plastic and timber fenders?

715


How do you prepare Material Recovery Statement for deduction from contractors bills?

1103


Any strength is a stress but any stress is not strength

1280


How do you measure concrete?

766


What is quantity of cement and sand required for 2000sqft of tiling?

2389


I am called for interview from north east power plant .so, I need some interview question which may help me.

1250