how much cement is required for 100 sft plastering of ratio
1:4
Answer Posted / karthikeyan.n
1 sq.m = 10.76 sq.ft.
100 sq.ft = 9.29 sq.m
cement required for 10 sq.m = 3/(1+4)=.6*1440/50 = 17.28bag,
100sq.ft cement required = 1.728*9.29 = 16.05 bags
Is This Answer Correct ? | 34 Yes | 93 No |
Post New Answer View All Answers
What is made from large rocks, which protects the base of cliffs?
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
what is Bearing Capacity,How to determine it?
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
How many types bend used in civil reinforcing
How to calculate density of 40 mm coarse aggregate, in mixing ration 1:1.5:3? Please explain calculation for density
What is the Maximum %age of Steel in columns and beams ?
How do you calculate the power of centrifugal pump?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
Explain the advantages and disadvantages of using plastic and timber fenders?
How do you prepare Material Recovery Statement for deduction from contractors bills?
Any strength is a stress but any stress is not strength
How do you measure concrete?
What is quantity of cement and sand required for 2000sqft of tiling?
I am called for interview from north east power plant .so, I need some interview question which may help me.