how much quantity of work we can get by rod benders per day
Answer Posted / sunil
as per my experience..in building..rod bendender do do
quantity...only 3 tons(the steel only less and small dia)
in bridges.1.5- 2 tonn( in slabs and abutments )
including binding also
Is This Answer Correct ? | 0 Yes | 14 No |
Post New Answer View All Answers
Minimum and maximum size of the building components
mix design procedure for 1:6 cement mortar
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings
what"s the sort of beams?
Which is the most prominent tower of world?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
what is the coefficient for running feet to cft coversion both area and price
Curvature ki quantity kaise nikalte hai pls give me ans... curvature canal ka hai
Scaffolding IS code NO.
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
What is the worlds largest concrete dam?
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
Is it possible to make a feature using an overdefined sketch?
what is Short bored pile foundation.
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.