plz answer the questions, How do you check the quality of
foundation? and What is the key performance area in quantity
survey?
Answer Posted / dinesh.rk
1>as you know the quality (strength)of foundation is assed
by testing that cube specimen and by quality control during
casting the foundation/
2> there is no such a particular area.. what we need is THE
ACCURACY SHOULD BE 100 % IN EACH AND EVERY ITEMS OF WORK/
Is This Answer Correct ? | 7 Yes | 1 No |
Post New Answer View All Answers
What is the average density of soil?
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
What is thumb rule in quantity and cost estimation of a residential building?
what is concrete canvas?
What you understand by richter scale?
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
For submitting the project loan for bank Residential bldg,Suppose we take Provinding RCC mix 1:2:4 for footings No of footings,length ,Breadth,Height ,qty in cum, at last unit/Rate(Rs) ,i would like to know how do we get the unit/Rate
1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
what could be the production cost of 1 cum of concrete by CP30 plant
Sir how to find cutting length for footing steel bars in the shape of "u"
How to calculate the quantity of ingredients of M20 grade concrete?
if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel
How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton
How can we make a hole in a solid rectangle using solidsworks?