In ACS 1000 drive we used 12 pulse convertor.Why dont used
6 pulse or 3 pulse convetor
Answer Posted / k.linga reddy
The characteristic harmonics order of the AC current wave
form is h= np+_1 so the 12 pulse converter out put contains
lowest order harmonics 11,13,....becuase of the lowest order
harmonics in 3,6 pulse converters
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
The sodium vapor lamp is not glows when it is connected a distance of 5 meters above from gearbox, why ?
acb(AIR CIRCUIT BREAKER)NOT CHARGING AUTO
what is meant by tranformer impedance?
how does this job compare with others you have aplied for?
I PURCHASED A DEISEL GENARATOR SET OF AVR TYPE& RATING 125KVA BUT SOME TIMES THE OUTPUT VOLTAGE IS FLUCTUATING WHAT ARE THE PROBABLE REASONS GIVE ME
Anybody know how schematic diagram for reverse power relay? RPR for generator protection
What is a signal flow graph?
Explain the method to keep noises low in a control system?
dg started in plc mode and load taken later one battery terminal connection will be disconnected by loose connection what will happen for dg and shall we connect battery terminals while dg in load time?
Explain Active power,reactive power,how its related to each other , & inductive ,capacitive.
WHaT IS THE CONCEPT OF INDUCTION LAMPS IN MODERN LIGHTINGS, and HOW IT WORKS TO EMIT LIGHT ( AS NO ELECTRODES ARE PRESENT ) ?" COULD INDUCTION LAMPS CAUSE INTERFERENCE WITH COMUNICATIONS INTO A STORE USING INDUCTION LIGHTING ? WHAT IS THE BENEFIT OF USING THE LOW FREQENCY INDUCTION LAMP , VERSUS LED , AND VERSUS FLUORESCENT, AND VERSUS ANOTHER KIND OF LIGHTING . THANK yOU MOISES GUINDI
WHAT IS SHORT CIRCUIT STRENGTH OF 100 AMPS MCCB?
1.why we are using blocks in withoutgaplightning arrester 2.why we ar using bushing in withoutgap lightning arrestor
formula for calculation of switchgears(i.e. contactor, fuse, cb, relay etc.), if load current is given?
We have 90mX100m hangar with 16 no.of supporting pillar. It is required to provide power supply on all pillars. what is suggested earthing scheme for hangars.