Answer Posted / vishwa theja c
Commissioning Of Transformer
After finalization of the erection work the following tests
should be conducted:
Pre Test Inspection
Sample of oil taken from the transformer and subjected
to electric test (break down value) of 50KV (RMS) as
specified in IS: 335.
Release trapped air through air release plugs and valve
fitted for the purpose on various fittings like radiators,
bushing caps, tank cover, Bushing turrets etc.
The float lever of the magnetic oil level indicator (if
provided) should be moved up and down between the end
position to check that the mechanism does not stick at any
point. If the indicator has signaling contact they should be
checked at the same time for correct operation. Checking the
gauge by draining oil is a more positive test.
Check whether gas operated (if provided) is mounted at
angle by placing a spirit level on the top of the relay.
Check whether the conservator is filled upto the filling oil
level marked on plain oil gauge side and corresponding to
the pointer reading in MOG side. Check the operation of the
alarm and trip contacts of the relay independently by
injecting air through the top cocks using a dry air bottle.
The air should be released after the tests. Make sure that
transformer oil runs through pert cock of buchholz relay.
Check alarm and trip contacts of WTIs, dial type
thermometer, magnetic oil gauge etc. (if provided).
Ensure that off circuit switch handle is locked at the
desired tap position with padlock.
Make sure that all valves except drain, filter and
sampling valves are opened (Such as radiator valves, valves
on the buchholz relay pipe line if provided).
Check the condition of silicagel in the breather to
ensure that it is active and colour is blue. Also check that
the transformer oil is filled in the silicagel breather upto
the level indicated.
Check tightness of external electrical connections to
bushings.
Give a physical check on all bushing for any crack or
any breakage of porcelain. Bushing with cracks or any other
defects should be immediately replaced.
Check the neutral earthing if specified. Make sure that
neutrals of HV I LV are effectively earthed.
Tank should be effectively earthed at two points.
Check that the thermometer pockets on tank cover are
filled with oil.
If the oil temperature indicator is not working
satisfactorily, loosen and remove the thermometer bulb from
the pocket on the cover and place it with a standard.
Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
Define what is difference between fuse and breaker?
Is it required to do earthing in 2nd shop if earthed armoured cable is laid from 1st shop ?
How will polarity test of Dy5 Transformer ?
What are IP protections used for electrical panels, JB, equipments installed in explosive zones like Petrochemicals, Oil & gas
what are the precuation should be taken ahen installing power transformer,circuit breaker,current & potential transformer
Will an earth leakage trip be activated if the component or wiring is faulty on low voltage equipment.Example An electrical Cat Scarer placed in the garden and water gets into the wiring.
Which device is used for the source of emission of electrons in a crt?
Explain RLC circuit?
there is an alternator 480 k.w, 400v,50hz, 4-wire running on load having leakage alternator body earthed current 38 A. is it within acceptable limit? if yes then give reference if no then how to bring within specified limit
Q) Write VBscript code along with QTPscript code in QTP tool for below scenario 1. Launch yahoo site(i know) 2. Do loogin(i know) 3.Click inbox link(i know) 4.Go to every page of mail box and count no.of read mails and no.of unread mails(i know) 5.Store page numbers, read mail count and unread mail count in a new excel file sheet 6.Create 10 types of graphs on that data 7.Do logout and close site(i know) 8.Save new excel files with graph
what is diff btw electric,magnetic & eletromagnetic field
hi if anybody got model questions for cpcl Grade'A' electrical engineer position.send it to my mail please krishkumar22@gmail.com
what is sevice settings for mccb?How can be it setted?
what is spadar bar .why I use in DC generator.
How to select batteries required for ups and the inverter if we Known load? And how AH is selected of battery?