Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answer Posted / mhbkpr
We cannot deshutter in all type of concrete works. for e.g
footing, plinth, beam sides like we can remove within this.
But roof slab likes we need provide back proping before
removing.
Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
How to calculate plastering for elevated water storage tank
Wats the formula of eccentric footing and how was calculated from concrete qty
How many feet are in 4 square yards?
How do you maintain water pressure?
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
Why should you consider yourself fit to be hired by jindal steel.
Define What is made from large rocks, which protects the base of cliffs?
B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS
How much material is required for constructing a 2 Lane 2Km rigid pavement road
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
How and where are aqueducts built?
Define line type?
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you