Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?

Answer Posted / binu

concrete acheives its 60% strength in
7days and hence its considered safe to
deshuttter.

Is This Answer Correct ?    13 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?

1781


What quantity of 1.0 m3 bricks required?

666


Which prize is the alternative to the NOVEL Prize?

1884


What is binding spacing of the rebars at lapping zones.

618


how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?

3322






How will be cutting in timber plate size 600*400 column size

1245


significance of specific surface area of particles?

1792


How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated

1700


what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.

1845


what is mean by reestimation?

1363


what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)

1288


How do you prepare Material Recovery Statement for deduction from contractors bills?

1109


1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall

1933


how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?

2141


I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'