Answer Posted / m.shilpa
Density of cement is 1440kg/cum.
weight of 1 cement bag is 50kgs.
By dividing density by weigt of bag we can get number of
bags per cum.
Thatis 1440/50 = 28.8 bags.
we can do it in other form to.
1bag is equal to 35 litres of water
therefore 1cum =1000litres
total no of bags = 1000/35 =28.8 bags
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
though u r a civil engineer, y r u interested in tcs???
the distrubution system in water supplies is designed on the basis of avg daily demand peak hourly demand coincident of draft greater of B & C
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
what is hydrostatic paradox?
What is the likely strength of a 1:2:4 concrete mix?
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
What tor stands for in tor steel?
How to check slab shuttering level.? Or check list for slab ?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
What are advancements in civil engineering?
what are the values of compressieve strenght?
What is kn measurement?