Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / sathy
Concrete quantity = H/3 [ a2 + b2 + square root of a2 x b2]
H = height of the trapezoidal footing
a2 = Area of the bottom of footing
b2 = Area of the top of footing
| Is This Answer Correct ? | 68 Yes | 27 No |
Post New Answer View All Answers
How is make concrete cube?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete
WHAT DLC DESIGN IN CONSTRUCTION
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
Which percentage of carpet area use in plot area of office building.
how to control PQI (Project Quality Index)
how to remove the quantity of metal 1 and metal 2 in concrete
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
List out some of the software used in the construction sector to estimate cost and monitoring expenses?
what is the formula to find the diagonal shape stirrups?
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
is basic cost of the material includes tax?
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.