Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how do you estimate the # of bags of cement, sand & gravel..
if only given the volume of the project..

Answer Posted / brajesh kaurav

let the total volume of the concrete is = a
and let the given mix proportion is =1:1.5:3
then the quantity of the
cement required = a*(1.57/(1+1.5+3))m^3 = X m^3
where 1.57 is loose volume of 1 cum concret.
we know that density of cement = 1440kg/cum
quantity of cement in per cum in bag=1440/50=28.8bag/cum(in
loose volume it consider 30bag)
1 cubic metre = 30 bags
x cubic metre = ?
=(X*30)bag/cum

now, fine agg = 1.5*X(+5% of voids)
coarse agg = 3*X(+1% of voids)

Is This Answer Correct ?    10 Yes 8 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.

2041


sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.

1992


How to find CN by using arcgis 9.3?

2432


how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you

2603


can stub column take the load as main column

1916


what is civil enginnering & what you need of this course?

2241


i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like

2003


How to design staircase.plz tell me formula for the design the staircase.

1979


Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?

2143


how to create our resume?

2191


what is the minimum reinforcement provided in beams,footings,slabs? what is the minimum soil bearing capacity to design a multistorey building

2448


which red: used in roof teping, then use only cement

2022


The 4 main factors to start a construction project are––

2298


Explain the importance of moment of inertia?

1278


in the construction of residential building what type of tank are used?where?why & what is its purpose?

2385