Question what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?
 Question Asked In Companies :: ABB, L&T, Saudi Oger, Construction, l, Isher, Spectra, Strati,     < I also faced this Question! >
 Question Submitted By :: shaunpaulstar
  Answer Posted By  
 
Answer
Ratio=1:2:4(cement:fine
agg.:coarse agg.)
Sum of the ratio=1+2+4=7.

Total dry mortar for 1cum
cement conc.=1.54(it is fixed)
There for=1.54/7=.22cum

Then quantiy of,cement=.22 into
28.8=6.24 bags.

Sand=.22 into 2(ratio of
sand)=.44cu m.
Aggregate(shingle or bajri)=.22
into 4=.88 cu m.

Materialr for 1cum cement conc.
1:2:4.
Cement=6.24bags
Sand= 0.44cum
Agg.=0.88cum

Is This Answer Correct ?    43 Yes 3 No


 
  vishal rana
 
View All Answers
 
 
Please Help Members By Posting Answers For Below Questions
 
 Question Views   Select
 
Describe the role of independent Quantity surveyor? 1038
What is the zero value in quantity surveying 654
how to find ssm in foundation? 81
How much material will consume for following specification water tank (9*7.5*6 feet)? 425
What are the methods of measurement? Describe it shortly 604
how to convert sand in Cft to Kgs 12
how can economic during construction of a project. 408
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2 90
how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....? 85
How to calculate construction cost of residential building in mumbai 132
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done. 651
what is the water-cement ratio of mix design while 30mpa in 7 days? 1358
How to check slab shuttering level.? Or check list for slab ? 120
3. What are the disadvantages of your present job, things you do not like about it? 1050
What is chemical composion test 195
E-Mail New Answers        Answer Selected Questions