what"s the minimum content cement allowed in RCC?

Answer Posted / prakash kedia

for rcc minimum amount of cement according to is code
300 kg/m3 with th admixture
and the maximum amount of cement is 450 kg/m3 without the
admixture

Is This Answer Correct ?    8 Yes 7 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band

1412


how i get all type of short type question answer about civil engg

1289


what is the theoritical percentage of concrete cubes testing per day?

4394


hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com

1824


In the roof of a pumping station explain briefly the components of a waterproofing system?

690






List out the potential risk factors for workers on the construction site?

646


what is meant by csr in foundation? what is sbc?what is meant by contour line?

1833


How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/

1361


In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.

1813


how much one carpenter can doing shuttering of slab in one day

2885


What distance in meters on the ground is the equivalent of one second of arc in longitude or latitude?

649


beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?

1656


I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

1648


what is the types of surveying?which type of survey carrying for type of work?

1677


How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.

1010