How do you derive the quantity of cement & sand in brick work
construction in 1Meter cube, using CM 1:6 and bricks of size
19*9*9 cm
Answer Posted / sag
Volume of bricks with mortar=.2*.1*.1=.002
No of bricks=1/.002=500
Volm of 500 bricks=.19*.1*.1=.7695
Volume of mortar=1-.7695=.2305
Add 15% for wastage and 30% for dry mortar
Now volume of plaster=.2305+.2305*.15+.2305*.3=.334
1:6 cement and sand 1+6=7
Volume of cement=1/7*.334=.048m3=1.36 beg
Volume of sand= .048*6=.288m3
Is This Answer Correct ? | 33 Yes | 5 No |
Post New Answer View All Answers
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
What is geopolymer based concrete?
how to caluclate sienerge qty in construction in ap
Mention what are the composition of a landfill?
Civil engineering related
What are the RISKS during the project construction?
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
length where bent up is made in slab of bridge from one end
How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance
How many feet are in 4 square yards?
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
what is kribs is supporting?