What is a purpose of slow firing before commissioning of
bagasse based boiler. and what is the water requirement for
make up?
Answer Posted / a. nagaraja
Refractory work will be done in the boiler at the bottom
four sides, manhole doors,burner area, peephole area and at
the top of the boiler. To heat the refractory from low
temp. to high temp, slow firing is done. So that
refractory will be gripped. And also to remove the
unwanted particles like sand, rust, oil and others from
boiler tubes and headers slow firing is done.
TSP and NaoH chemicals will be added with D.M water and it
will be filled in the boiler. The prs. will raise slowly
up to max. 15kg/sq.cm
Is This Answer Correct ? | 21 Yes | 3 No |
Post New Answer View All Answers
what is an function of air cell bag in air cell conservator
diffuser increases pressure but in turbine pressure is decreasing when steam passing through casing?
how can I masurement the circale weight ? like- 312mm i/d x 392mm o/d x 6mm thick.
compare brayton and otto cycle
wap to insert an element in array at a particular location
pls, send me jindal steels & power aptitude ques
How should I begin a conversation that I need a change in the job to a known person in his organisation?
What is function (in details) room sensor and tube or coil sensor in HVAC system?
Causes of M/E high exhaust valve temperature
In General please do read newspapers.And be thorough with 10th history and Geography.Biology also
Which pipe should I use SAW, ERW or seamless if I have the following constraints I have to transport methane gas Size is 8” Corrosive environment Sulphide is present Also tell the cost comparison
Where do you work in engineering company?
What is difference between Higher calorific value and lower calorific value?
what is the difference in Gas Welding and Gas Cutting?? Second Question is for Huge Casting which method is used??
Differentiate between the uniform flow and non-uniform flow?