Answer Posted / sherin sunny
Refrigeration systems were first used to produce ice. The
capacity of a unit was how many tons of ice per day could
be made.
1 ton is the amount of heat that could melt 1 ton of ice
(2000lb) in 24 hours ex. it takes 144 btu of heat energy to
mellt 1lb of ice at 32F.
144btu/lb x 2000lb = 288000 btu < thats how many btus it
takes to melt 1 ton of ice in 24 hours
if an a/c has a 1 ton capacity it will remove 288000
btu/24hr or 12000btu/h
Is This Answer Correct ? | 12 Yes | 3 No |
Post New Answer View All Answers
Explain why you consider yourself suited for the Position:
Differentiate Between High Speed coupling and high torque coupling with examples.
WHAT IS A TR REQUIRED IF AIR FLOW 6500 CMH COIL INLET TEMP 7 - 12 DEGREE C AIR TEMP INLET - 18 DEGREE C & REQUIRED TEMP IS 12 DEGREE C
What causes crankcase explosion?
Plese give us information Service Special Tools for Hydraulic,Trasmission,Main clucth,Rear axle etc for Mahindra Tractor 6030-4WD,Like SST Number,Discription,Price and Dimension or Photograph if u have.Thanks
What are the causes of dirty lubricating oil?
Gegger is used in foundry for the purpose of____________
general diesel engine we are using 15w 40 oil unfortunatley our oiller mis used the oil hudralic oil refilled when he doing the service which kind proplem coming in future?
There is a block placed in between air and water. water is at 100 deg cel and air at 50. 1) Draw temperature profile. 2) Why is it curve in air and water?
What are topping and superposed turbines?
What is mean carry over of Aux. Boiler?
what are the main problems of solar electrical systems? to make quality control on, which parameters that need so?
pl convey me the procedure to get the vat and cst no. i am going to start trading cum manufacturing of grain handling equipments.
How do you calculate cooling energy?
1.how do you purchase the sheetmetal,machined components for OEMS? 2.WHAT IS THE SYSTEM TO BE MAINTAINE FOR PURCHASE ACTIVITY? 3.HOW DO U DO THE PRICE NEGOTIATIONS & ITS PROCEDURES? 4.WHAT ARE THE PROBLEMS WILL FACE WHILE PURCHASING THE COMPONENTS& WHAT IS THE SOLUTION TO OVERCOME BY THAT ONE 5.WHAT IS THE NECESSARY NOTES TO MAINTAIN THE PO& RELEASING THE PO?