1 building project (work in progress) and following are sum
detail about his project
1) Using local rebar grade 415
2) Total built up area- 60000 sq.ft
3) Floors to be constructed – 21 storey
4) Estimated requirement of Steel per sq. foot –
7KG/sq.ft
5) Concrete grade – M35
6) Rebars mainly required (sizes)- 16,20,25,32 & (8 mm
for stirrups)

Wanted to ask u if this person uses 500D…what are the
benefits he will be getting? Whether his per Sq. foot
consumption can b reduce? If yes den around how much?

Answer Posted / wicked_dipen

plz ny1 help me in finding this answer

Is This Answer Correct ?    3 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Gidc technical que paper

1260


For the construction project what capital cost has to be taken in consideration?

678


Define What is passive earth pressure ?

697


How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?

1563


in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing

3352






How much is the cover for slab?

740


what is labour consume factor in residential projects

1857


undistributed samples are obtained by

2001


from where ican get sample papers for CET-delhi 2012

2044


Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?

2042


What are advancements in civil engineering?

652


how much is the maximum compressive strength of soil cement and soil-cement-microsilica .

1824


What quantity of 1.0 m3 bricks required?

666


How to calculate the load of partion in flat slab if we use brick?

1393


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?