Answer Posted / eng. d
I like the answer which is talking about the cu losses and
characterstic of the transformers.
let me drive the answer from differint angle.
let us assume that we told you that, the transformer is 20
MW, and now you want to connect motor of 15 MW to this
transformer, are you able to start this motor from this
transformer before the protection setting trip the circuit
breaker of the transformer?
I don't really know!! because I don't know how much
reactive power in this transformer, in other words, I don't
know how much losses in this transformer, then I can't do
prpoer analisys of the motor starting without knowing the
MVA rating.(which will include active and reactive power)
my advice, please try to do motor starting analysis on ETAP
or Matlap or any electrical softwaer and play with the
reactive power and see the differance and you will be clear
more ^_*
good luck
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
Draw a circuit diagram in which if button is open we can use socket and bulb as a series test circit and if button is close than simple we can use socket as any load purpose.
in a solar power plant,we are going to step up the voltage 350V to 33kv, and to 132kv GSS. i want to ask that if it is possible that 315v/33kv is not possible because we also use 315v/11kv. or it should be 415v/33kv? is it effects generation or losses? the second question is-generation is depends on LV winding? or LV winding design for generation voltage?
how to calculate mf when meter and cTPT detail are given
what is consequences of neutral and earth connect?
what exactly commisioning work does in electrical site work... LT side?..
Difference between rating factor of cable and derating factor of cable?
What is the suitable transmission voltage?
What is time invariant system?
Is there possible to Test Transformer for Overfluxing Capability. Or is there any firm who does Overfluxing Test on Transformer?
why you don not show protection and type of isolation in key single line diagram?
hi can any body send me syllabus of rrb electrical section engg... and past pepar also of any board...
what are the Alarm, Trip & Safety equipment (Issues) present in Power Transformers pls Mail it to ashokbabunhce@gmail.com
Whats the difference btwn a latch, port,data bus buffer? Do they all not hold data in d flip flops??
can any tell me why slope 40% and 80% is calculated in differential protection?
Zone of protection and tripping scheme of arc protection relay.