what"s the formula to find the cement,sand,aggreegate(45mm)
requirement for PCC?

Answer Posted / suresh

for ex 1 m3 of concrete
conc 1;4;8
cement = 0.45 m3 of mix =1440x0.45/4=162kgs or 3.24 bag
sand = 0.45m3
40mm aggregate = 0.90m3

Is This Answer Correct ?    22 Yes 18 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

punj loyed and sapurjl palanjl

1888


What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code

1620


What is the meaning of soil reinforcement?

668


What was asked in isro civil interview

504


a butt weld is specified by

2593






I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

1649


what is the percentage of silt in black cotton soil.?

1962


Explain what is Hybrid Foundation?

746


what is meant by residual strain?

1802


How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?

1371


In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed

2706


Why are steel plates inserted inside bearings in elastomeric bearing?

838


Types of column foundation and how to calculate its steel quantity.

1447


Material calculation of cm 1:6 for 1sqm

1506


why development length = 50D . why not 100D

1482