how many no of cement bags required for 1:4 plastering for
100 sqft?
how many no of cement bags required for 1:3 plastering for
ceiling for 100 sqft?
Answer Posted / lawrence.m
We assume the thickness is approx. 0.5inch. So that the volume is 100sqftx0.5=50cft(1.416cum).
For 1 cum( CM1:4), 1/5x 1440= 288Kg cement required.
Therefore, 1.416cum = 407 Kg required(Approx 8 bags)
For CM 1:3, = 510 Kg (Approx. 10 bags)
Is This Answer Correct ? | 10 Yes | 58 No |
Post New Answer View All Answers
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
What is the difference between engineering stress and true stress?
Why steel rods are produced only in even dimensions?
is basic cost of the material includes tax?
Define the various stages of the project planning process in construction.
How many cement sand ballast in cc 1:4:8 40mm
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
How to come 1.54 from dry to wet concrete?
Tell me about triple point of water.
Why was the empire state building made of steel?
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
how u design STAGING for Superstructure in BRIDGE construction?