Answer Posted / pradeep
Honey combed concrete repair by
1. Pressure grouting with Polymer cement slurry. than
2. Filled up surface with epoxy or polmer mortar and
levelled it.
3. or by laying of mastic of 20mm or more thick and compact
it
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L
How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
Explain how you can use different dimension tools in CAD? What are the different dimensions available?
Detection of a beam & a girder are––––
What is the difference between yeild strength and compressive strength of steel???
what are the ffactors you considered choosing the course?
Give list of building construction equipment & explain about them in brief. How much is output of JCB, POCLAIN, Steel cutting & bending machine, material hoist, tower crane?
Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.
how to shuttering is used in slab
why does the most of civil engg is not intersted to going for teaching field?
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
afe or not
How much wastages taken in 1. cement 2. steel 3. fine aggregate 4. coarse aggregates (10mm, 20 mm)