What are the steps for Testing of 6.6KV HT Panels?

Answer Posted / siva prasad

1. Check the panel alignment
2. Check the panel wiring as per scheme diagram
3. Check the continuity of Panel wiring
4. Check the meggar values of Bus bars and HT cable
5. Check the millivolt drop test of bus bar
6. Check the status of breaker
7. Primary and Secondary injection, Polarity tests for CT
and PT of bus bar
8. Set the time for fault current objection in relay
9. Knee voltage Test depends upon CT
10. Check DC supply permanent are temporary.
11. Physical inspection for satisfaction

Is This Answer Correct ?    18 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is a composite error in current transformers, why occurs & in which it will occur i.e, either metering ct/ protection ct

1302


explanation of mesh bus bars

1687


what mean by analog ,digital,numerical meters and relays? say the example?

1765


what is Fault level? why it is calculated? how will u decide same for our plant?

1573


Type of motor stater detail and working detail

1270






Difference between control junction box (cjb) and power junction box(pjb)?

3002


what id a dry type transformers and its function ?

1350


Is vtg is controlled by the resistor? if else how much?

1655


IF DISTANCE IS 100METERS B/W AMP.METER AND CURRENT TRANSFORMER WHAT WILL BE AFFECT IN ACCURACY .METER CAN SHOWING ACCURATE CURRENT OR NOT IF NOT WHAT CAN I DO TO GET 100% ACCURACY.

1421


how to measure earth resistance of a substation

2745


What is the equivalent circuit of a transformer and its vector diagram?

2179


WHAT IS THE TECHNICAL SPECIFICATION OF C CURVE & D CURVE LEGRAND MAKE MCB

2086


How many types of colling system it trformers?

726


After completing iti in electrician, how can i get certificate of electrical supervisor? What ia requirements. For it?

1285


how braking & making capacity of circuit breaker are calculated?

1853