How to calculate the no of bags required for 12mm thick 1:6
plastering?
Answer Posted / dinesh
Cement= 1 Sand = 6, assume W/C=0.4
Water = 0.4*1= 0.4
Total = 1+6+0.4=7.4
Wt per m3 of CM = 2400 kg
for 10 m2 = 1.2 cum CM reqd.
Cement required for 1 m3 = 2400/7.4 = 324.3 kg = 6.48 bags
so for 10m2 area of 12mm thick plaster = 1.2*6.48 = 7.78
Bags required.
| Is This Answer Correct ? | 13 Yes | 27 No |
Post New Answer View All Answers
What is the veriplus for ellips card length formula (major axis 3.4m,minar axis 2.6m spacing 0.2m
What applicable rate of wct in bihar
How much cement will require for 1Rmt Skirting laying
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?
Define aligned dimension?
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
How many axes do cartesian coordinate system has?
What is the use of array command?
Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......
Cement consumption of one cubic meter of aerocon blocks masonry?
If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
mix design procedure for 1:6 cement mortar
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20