How many no of cement bags required to do the concrete with
the proportions 1:1.5:3 for 4inch thickness for 100 sqft?
Answer Posted / balvinder bhagat
Convert area of slab (100sqft)into sqm = 100/10.76
=9.29 sqm
(as 1m2=10.76 sqft)
thickness (4 inch) =.1m
Volume =9.29*0.1 m3
=0.929 m3
As in 1:1.5:3 for 1m3 no.of cement bags =8 bags
Therefore,tot. no. of bags =0.929*8
=7.43
~8 bags.
Is This Answer Correct ? | 32 Yes | 2 No |
Post New Answer View All Answers
List out the types of roofs?
02. a. The diagonal of a 9 cube…………… 1 b. Surface area of 9 cube…………… 1 c. Volume of 1-3 cube …………… 1 d. Compressive area of 6 cube …………… 1 e. Top & Bottom face of a Cylinder/Cube is to be proper leveled to deliver the…………………………..…… properly.
rate analysis for cement pointing 1:4 , for 100 sq m
what is the anchorage length of reinforcement.
Define What happens to Load at yielding ?
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
how to calculate quantity of bricks in circular manhole with examples.
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
how to find hardness of water?why it should be determined?
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
How much quantity of cement,sand,stone used to build 1 cum of cc road??
what does the grad of cement shows (denotes)?
what's the formula for calculate pcc for matt(45mm aggregate)?
what is meant by shear center?????
Why should appointment store person for project ? what is the benefits for company ?