HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC
METER.
Answer Posted / praman kr srivastava
Mistry I No 0.200
Beldar Nos 3.000
Bhisti No 0.900
Sundries L.S 5.500
Is This Answer Correct ? | 5 Yes | 7 No |
Post New Answer View All Answers
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
what is the procedure of wet seiving. n percentage of silt in different type of soil?
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
What are some structures that may be subjected to fatigue?
why development length = 50D . why not 100D
what is the water cement ratio? how to calculate it? list the wt. of constructions materials including concrete both ordinary and light wt. concrete
What is thumb rule in quality and quantity estimation of a Residential building??
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
how we can find sieve #4 is 4.75mm?
what is E
How can you achieve soil enforcement?
why is M30 grade Concrete use for Foothing & Column M50
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
please briefly explain calculating or estimating steel quantity for a RCC column?
What are the different types of civil engineering?