Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC
METER.

Answer Posted / geethu

can u explain ? Head mason - .05 x Rs 200 = Rs 10.00
Mason - .3 x Rs 190 = Rs 57.00
Labour - 2.5 x Rs 90 = Rs 225 ? wht"s mean by 0.05?

Is This Answer Correct ?    24 Yes 18 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what will be density of a cement bag if its weight and volume are 50kg and 1.25 cft respectively???????

2133


quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data

3174


how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution

2169


how much to get of BRC lapping in full yield and half yield ?

2559


Define What is made from large rocks, which protects the base of cliffs?

1091


How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir

1569


What is meant by cartesian coordinate system?

1180


about higyway engineering

4435


Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire

1653


1:4:8 pcc calculation 591 cu.ft

2311


i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............

3144


Differentiate first angle & third angle projection?

1145


How to do rate analysis for concrete work including shuttering work?

2058


The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.

2738


How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?

1700