what"s the purpose of dry lean concrete(DLC)and where it"ll be
use it?
Answer Posted / sjtbehera
A plain concrete with a large ratio aggregate to cement
than structural concrete. It is used for filling and not
structural duties
| Is This Answer Correct ? | 45 Yes | 8 No |
Post New Answer View All Answers
How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir
A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
Please tell me vasthu room sizes. Thanks.
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
What are the disadvantages while using stone dust as filler in pavements?
we have a crushing plant and our product is experiencing flakiness and elongation over limit for granite. what is the solution to this problem? how can it be avoided and what to do differently? It is not ok for batching plants
What is progress payment?
Is there the dry coefficient of cement is constant?
what is Short bored pile foundation.
Describe the role of independent Quantity surveyor?
in 100 cft = 1350 bricks in 100 cft = ? bloks
show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?