Set the slump cone and fill with concrete mix at 3 layers
and tamp by using the 16mm Plain round bar 25 times each
layer but be sure not to touch the previous layer. Remove
excess concrete on last layer then carefully remove the
cone vertically and place beside the concrete mix. measure
the slump by a measuring device the compare to the
specified slump height.
Concrete cubes is performed by mixing water, cement and
sand in a portable concrete mixer. place the mix in 3 sets
of 2"x2"x2" steel mold, 3 cubes each set then mark each set
for 3, 7, and 28 days. Place the cubes in a curing pan
after removal from the mold when hardened then test it for
3,7 and 28th day age for compressive strength determination.
Is This Answer Correct ? | 5 Yes | 1 No |
Post New Answer View All Answers
What do you mean by bond? What are the different types of bonds?
how to take concrete quantity for precast segment for viaduct project?
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
What is the difference between built area and super built up area?
How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight
Explain the various stages of the project planning process in construction?
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
What is meant by cartesian coordinate system?
Define block?
Define What is the difference between routing maintenance and major maintenance in school facilities?
Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)
How is the leaning tower of pisa supported?
Explain the mechanism of cavitations in pipes and drains?
What is the diff between cad & cadd?